:: Crossing Interstate 93 without Stopping Traffic Call us at 1-866-HDD-BORE

Commercial Projects

 I93 Concord Project
 Nantucket Runway
 Chelmsford Water Main
 Goffstown Water Main
 Franklin Rock Boring
 Nantucket Cable Project



Residential Projects

 Dover
 Richmond
 Boscawen
Project Photos
I93 Photo 1 I93 Photo 1 I93 Photo 8 I93 Photo 13
"Without directional drilling, this kind of project would seem impossible. In reality, it was a very simple and cost effective option."
- Jeff Martin
:: Crossing Interstate 93 without Stopping Traffic ::
Everyone knows what a hassle it is when a highway is under construction. We'd never make it on time anywhere if a road had to be shut down every time a utility needed to be extended across it. Fortunately, directional drilling can happen so invisibly that drivers aren't inconvenienced and utility companies don't have to pay for road reconstruction.

In March 2005, Henniker Directional Drilling (HDD) crossed Interstate 93 in New Hampshire, a north/south road that runs the length of the state from Massachusetts to Canada. Working as a subcontractor for East Coast Utilities, HDD's job was to install an 8-inch steel sleeve for Keyspan Corporation, a gas utility company. The crossing took place at exit 16, a busy area north of the capital city of Concord, NH.

"Cutting through the road and rerouting traffic would not have been a good option on this section of the interstate," says Jeff Martin, president of Henniker Directional Drilling. Instead, Martin and his crew Charlie Hunt and Corey King set up the 50 x 100 Vermeer rig and a vacuum truck on a dead end side street off the exit, away from highway traffic.

Using a 14-inch reamer that cut through silty material and a few gravel seams, the bore was completed in a single shot in just four hours. The next day, a 335-foot steel sleeve was installed 22 feet under I-93. The job took just two days - a fraction of the time it would have taken to shut down part of the interstate, reroute traffic, open cut the road, haul away material, and reconstruct the road.

Tracking the bore head across the busy highway was the only challenge Martin's crew encountered. To avoid large volumes of traffic, the crew began working after morning rush hour. To keep the crew off the road, the bore head was tracked to the edge of the road, kept on course, and relocated at the median. Corrections were then made before crossing the next two lanes.

For safety, NH State Police were on site and the NH Department of Transportation regularly monitored the job's progress and safety. Because Martin's crew was located off the highway except during bore head tracking, traffic was never stopped during the process.

"Overall, the job went very smoothly and we all enjoyed working with such quality contractor and professional crew," says Martin. "In this case it was less expensive to bore than open cut."

"Our only real pressure was getting the job done before a huge snowstorm hit the city," continues Martin, whose team helped lay the infrastructure for a gas line into a building that had been sustaining on propane during the cold winter.

Copyright © 2005 Henniker Directional Drilling Call us at 1-866-HDD-BORE Design and Maintenance by Codify Online

Active drilling into a typical size entry pit. The drill steel will follow the drill head as it is steered under I93.

Driller on the Vermeer 50 x 100

Photo 8

President of HDD, Jeff Martin using the vacuum truck to remove the drilling slurry